Requirements for the usage of high-speed braiding machine

Safe operation procedures for high-speed braiding machines:

  1. Before starting the braiding machine, check whether there are any abnormalities in all parts of the braiding machine server. Fill each lubricating part with lubricating oil as required, perform an air-open operation, and wear protective equipment.
  2. After the wire is tied through the guide wheel to the bottom of the pot and braided to the conductor, it is then put into the reel through the driving wheel, and after being fixed, starts driving.
  3. After each shift, the dust, oil stains, and broken joints on the wheel slide rail surface, curve groove, left and right spindles and swing rods should be cleaned immediately.
  4. When the braiding machine is running, attention should be paid to observing the machinery and equipment, and frequently checking whether the lubricating oil can successfully reach the lubrication point from the pipeline. The rotating components of the lower swing arm support frame must be filled with salted butter and must be filled with salted butter after every 120 hours of operation.
  5. Any operating components of the equipment that cannot be touched by the automatic lubrication system should be lubricated manually from time to time. The pitch interchangeable gears, telescopic gears, and traction belt gear rack parts should be added with industrial grease once per shift; the main rod of the cable arranging device should be filled with industrial engine oil several times per shift; the main rod of the cable arranging device and the coil The spherical bearing injectors on both sides of the line positive transmission gear should be oiled once per shift.
  6. If an unknown shutdown occurs, the alarm flashing light signal generated on the “Fault Alarm” interface can be used for corresponding clearance; if a shutdown without alarm occurs at the same time as the oil pump alarm setting time, the oil pump and oil passage should be checked. Is it normal? If it is found that the lubricating oil cannot reach the lubrication point, fault detection is required before restarting.
  7. When the equipment is running, it is not allowed to replace the hanging wheels. Always pay attention to whether all parts of the equipment are operating normally. Operators are not allowed to leave their posts without authorization or let people without work certificates operate. If there is an abnormality in the equipment, stop immediately and please Maintenance staff help to deal with it before driving again.
  8. After the work is completed, turn off the main power, clean the work area, remove the lint and dust on the bottom of the flower pot, wipe all parts of the equipment, store the remaining hanging wheels in the designated area, place them neatly, and fill in the process flow Cards and various financial statements and records, and do a good job in handover work.

High-speed braiding machine process operation rules:

  1. This procedure is applicable to the weaving process of rapid braiding machine production of shielded variable frequency cables, plastic wires, radio frequency coaxial cables, etc.
  2. Equipment technical standards and main parameters: “Equipment Instruction Manual” of the detailed braiding machine.
  3. Production equipment and star measuring instruments: Measuring instruments: Vernier caliper with a precision of 0.01mm. Special tools: scissors, wrenches, screwdrivers, etc.